Onshore preparation works at Sizewell.
Over the next weeks we will be carrying out site preparation works to prepare for the construction of the access road to Galloper’s onshore electrical infrastructure. This will be an extension of the existing access road through Sizewell Wents Woodland from Sizewell Gap.
Ahead of the main works, we will be undertaking tree felling beginning on February 24th.The work is being undertaken before the start of construction to avoid the bird nesting season. We expect the work to take two to three weeks. An ecologist will be onsite and all trees will be thoroughly checked for any bird or bat presence before tree felling commences.
The works will be restricted to take place between the hours of 7am – 5pm, Monday to Friday.